The drawings on page 4 are the extracts from a technical file for the construction of a reinforced concrete structures to
carry two water reservoirs for a secondary school in Community
. The structure is made up of 4 identical footings of 80cm
x 80cm
lying on a lean concrete of 5cm thick. It has 4 ground Beams just immediately after the ground level. The
dimensions of the structural elements are as show
n on the draw ings.
Evaluate the surfaces of formw ork for the following:
a
) Tire reinforced concrete pillars.
b)
The reinforced concrete ground beams.
c) The
reinforced concrete floor.
d) The reinforced concrete upper beams.
e) Total surface area of fomrwork.
(6 marks)
(4 marks)
(
4 marks)
(
14 marks)
(
4 marks)
Total (40 Marks)
Question 2
After technical studies
of a certain project; the following information was obtained:
Table 1: Quantities

S/N Designation Unit
rn
Quantity
1 Excavation 142

777
2 Lean Concrete m 17.6
i
3 Reinforced Concrete m 38
4 Formwork
nr 82

5 Striking formwork
6
nr 78
Reservations
7 Water
proofing
m
m
8
48

8 Backfilling m 96
Table 2
: Batching of concrete for a 1mJ

S/N
I
2
Designation
Lean concrete
Reinforced concrete
Cement
150kg
350kg
Sand Gravel Reinforcement
4001
4201
8001
8001
120kg
Table 3: Unit time designation
S/N Designation Unit time S/ N Designation Unit time

1 Mixing of concrete 5.5h/m6 Striking of formw ork 5.5h/nr
2 Casting of concrete 41i/m 7 Striking of formw ork reservation 5.5h/nr
3 Formwork 51i/nr 8 Placing of water proof 5.51i/nr
4 Reinforcement 75h/ton 9 Excavation 5.5h/m

5 Reservation 16h/nr 10 Backfilling 5.5li/rn
Work to be done

a) Determine the quantity of cement, sand, gravel and reinforcement for the project 3×4= (12 marks)
b) Evaluate the time spent for; excavation, lean concrete, reinforced concrete, formw ork, reservation,water proofing
2.5
\6 = (15 marks)
c) Deduce the labour hours spent for:excavation, lean concrete, reinforced concrete, formwork, reservation and water

proofing. (3 marks)
Total (30 marks)