cameroon gce A level 2024 building construction project management 1
cameroon gce A level 2024 building construction project management 1
PERT technique of network analysis is mainly
useful for.
A small projects
B large complex projects .
C deterministic activities
D research and development projects
Who is an initiator of a project?
A Client
B Engineer
. : < C Architect
D Quantity Surveyor
9.
A critical activity in the planning of a project is
A An important activity
B A commanding activity
C First activity
D Last activity
10.
2. The main factor to be considered while
preparing a detailed estimate, is.
A Transportation of materials
B Proportion of mortar
C Specifications of works
D Proportion of cement Which of the following approximation for a
calculated volume is correct?
A 16.2352 cu.m (m3)
B 16.235 cu.m (m3)
C 16.2350 cu.m (m3)
D 16.24 cu.m (m3)
I I .
The most suitable type of equipment for
compaction of cohesive soils is :
A Smooth–wheeled rollers
B Sheep foot rollers
C
: Vibratory rollers
D Tampers
J .
12. C.P.M. is
A time oriented technique
B activity oriented technique
C Target oriented technique
D Event oriented technique
4. The difference between the time available to do
a job and the time required to do a job is known
as
A Event
B Float
C Duration *
D Constraint
Pilfering on a building site is
A A natural phenomenon
B An artificial phenomenon
C A natural and artificial phenomenon
D A progressive phenomenon
13.
5. Which of the following is not a contractor in the
execution of a project?
A A person
B A firm
C An agency
D Supplier
14. Contract documents are principally grouped in
to
AB
4
C 2
6. Depreciation is define as D 5
A Increased in value of an equipment
B Lose of value of an equipment
C Total lose in value of an equipment
D Reduction of value of equipment.
15. In big contracts, who represents the architect on
site?
A Project engineer
B Clerk of works
C The site foreman
7. On the site, the engineer represents the interest D Control engineer
of
A Delegating contracting authority
B Architect
C Contractor
D Client
The process of inspiring subordinates to do
work or achieve objective is known as
A Management
B Supervision
C Motivation
D Communication
16.
>
The minimum number of members in a
technical sub committee of the tender board is
A 3
B 1
C 4
D 2