- Which of the following is the correct metric unit
for quantities
A Volume for length
B Cubic metres for area
C Square metres for volume
D Litres for volumes
- In planning, the critical path
A is the longest
B is the shortest
C may be the longest
D may be the shortest
- A site machine most suitable for digging under
water is
A Drag line
B Hoe
C Clam shell
D Dipper shovel
- The principal factor to be considered while
preparing a detailed estimate is
A Transportation of materials
B Proportion of mortar
C Specifications of works
D Proportion of cement
- A suitable site equipment for compaction of
cohesive soils is
A Smooth-wheeled rollers
B Vibratory rollers
C Sheep foot rollers
D Tampers
- What is the length of a window whose
dimension is written as 1.20×1.60
A 1.60
B 1.20
C 2.80
D 1.92
- The surface area of any building construction
element is calculated to
A 1 decimal place
B 2 decimal places.
C 4 decimal places.
D 3 decimal places
- Authorisation to partially block a road when a site is
located in a built area is taken from
A The police
B The gendarmerie
C The delegate of urban affairs
D The mayor
- Which of the following is not written on the
sign post of a given project?
A Duration of project
B Name of project
C Cost of project
D Funder of project
- The minimum height recommended for a site
fence is
A 1.50m
B 2.00m
C 2.50m
D 3.00m
- Site gates are opened
A Into the site
B In or out
C Into the road
D Not always opened
- What is the diagonal of a square plot whose side
is 25m?
A 35.53m
B 35.35m
C 5.00m
D 625m
- The quantity of timber is measured in
A Kilograms/meter cube.
B Kilograms.
C Cubic meters.
D Square meters.
- Which of following is an administrative duty on
the site
A Preparation of formwork
B Hiring of a concrete mixer
C Correcting construction error
D Batching concrete
- The amount of productive labour hours required
to complete an elementary unit of work is
A Duration of an Operation
B Project time
C Hourly Consumption
D Unit Time:
- Decreases in material quantities due to transport
or handling on site are called
A Losses
B Poor handling
C Depreciation
D Transportation error