cameroon gce advanced level 2025 work organisation 3
cameroon gce advanced level 2025 work organisation 3
SUBJECT
AP
As a graduate with an advanced vocational certificate, the “C & L” fashion house where you dropped an application for a job wants to test your skills by offering you a contract to sew 2700 dresses for their customers.
WORK CONDITIONS
- The dresses will be launched on multiple lines by a team of nine (9) workers.
- The workshop allocates the speed below to the various workers, against the names respectively:
NO | WORKER’S NAMES | WORKER’S SPEED |
1 | Candy | 111 |
2 | Ruth | 104 |
3 | Rosa | 94 |
4 | Peace | 110 |
5 | Nadish | 105 |
6 | Julia | 95 |
7 | Lizy | 103 |
8 | Lydia | 108 |
9 | Romia | 98 |
- Workers work 5 days per week.
- The daily working time of the team is estimated at 7 hours 45 minutes.
WORK REQUIRED:
1) Calculate:
a) The base of fragmentation of the team,
b) The work value of a dress
c) The total time needed to sew the 2700 dresses.
d) The average speed of the team.
e) The number of dresses to be sewn by each worker, for a period of 21 days.
2) Complete the table below extracted from the balancing chart.
POST | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
WORK LOAD | |||||||||
WORKER’S NAMES | |||||||||
WORKER’S SPEED | |||||||||
SATURATION RATE | |||||||||
IDEAL SPEED | |||||||||
EFFECTIVE TIME |
3) On a table, present the necessary supplies for the realization of the dresses.
4) Present the production flow chart of “LIZY” model according to the mounting range given.
5) Calculate the global deadline for the series, expressed in days, hours, minutes and seconds.
NB: All drawings should be traced with black ink.