Choose which is not a personal protection safety
gear:
| A | Neck tie. |
| B | Overall. |
| C | Safety helmet. |
| D | High reflective safety jacket. |
______________________________________________
2. Site installation starts with:
| A | Delivery of plumbing fixtures to the site. |
| B | Ordering of piping materials. |
| C | Site visit. |
| D | Desk top activity. |
______________________________________________
3. Work planning involves:
| A | Elaborating the chronogram of activities. |
| B | Elaborating the time schedule. |
| C | Elaborating the purchase order, personnel need, equipment. |
| D | All of these. |
______________________________________________
4. Choose that which is not a safety condition when
using ladders:
| A | Always face the ladder when climbing and descending. |
| B | Back the ladder when descending. |
| C | Check that the ladder is in good condition. |
| D | Make sure that the ladder extend above the targeted work point |