cameroon gce A level 2024 work organization 3
cameroon gce A level 2024 work organization 3
“EVAN” MODEL SIZE 40.
r
DESCRIPTION
“EVAN” model is a fitting flared gown with
raglan short sleeves sewn with Gabardine
fabric.
FRONT
-Princess line from the raglan sleeve and ends
above the hip line.
– Shawl collar.
-Buttoned up to the hip line and a seam line down
to the hem.
-Belt at the waist.
BACK
– Princess line from the raglan sleeve and ends
above the hip line.
– Shawl collar.
Documents to be handed by candidates at the end
of the paper.
– Product analysis.
– Balancing chart.
– Theoretical implantation.
MARK DISTRIBUTION
1. Calculation
2. Study nomenclature 20 marks
3. Product analysis—
4. Balancing chart—
5. Theoretical implantation— 04 marks
SUBJECT
A manufacturing enterprise receives a command of 8500 gowns: “EVAN” MODEL knowing that:
The enterprise has a team of 10 workers working at an ideal speed; the launching is done in simple continuous
lines, Range ±6%.
> Garments launched in “packets of 10”.
> Daily working time:
• First shift: 7:30am to 12:30pm.
• Afternoon shift: 1:00pm to 5:00pm.
– Workers work 5 days per week.
– Due to the adaptation, the work is made in the following speed: 1st day: the production will be 95% and
100% for the other days.
WORK REQUIRED:
From the model and the mounting range given:
1) a) Determine the passing time of the first article as well as the evacuation rhythm of other garments;
by calculating the pitch range (BF) at ±6% and the daily working time.
b) Calculate the number of packets and the production done on the 1st day: 95% and 100% the other
days.
c) Calculate the fabrication deadline expressed in days, hours, minutes and seconds.
2) Establish the product analysis.
3) Present the balancing chart and calculate for each post:
a) The load.
b) The saturation rate.
c) Install the workers at their posts,
c) Calculate the effective time of each post.
4) Present the theoretical implantation.
Ruth
January 13, 2025
Please for the answers