cameroon gce advanced level architectural project management 1
cameroon gce advanced level architectural project management 1
Which of the following machines is used for
excavations in water below its wheels?
A Bulldozer
B Back actor
C Scraper
D Face shovel
_____________________________________________
2. An embankment blocks light into a classroom.
Which of the following machines will be used
for its excavation?
A Dragline.
B Face shovel.
C Skimmer.
D Tractor shovel.
_____________________________________________
3. A person or group of persons who apply for a
contract to be executed is called?
A A contractor.
B The engineer.
C The client.
D A bidder.
_____________________________________________
4. A delegated contracting authority is:
A The architect.
B The project owner.
C The representative of the project owner.
D The representative of the public works
delegate.
_____________________________________________
5. The length of a plot is twice the width. Given
that the surface area of the plot is 800m2. What
is the width of the plot?
A 20m.
B 16m.
C 40m.
D 19.80m2.
_____________________________________________
6. A machine used to clear ditches and streams is
called?
A The skimmer.
B The angle dozer.
C The drag lines.
D The bulldozer.
_____________________________________________
7. Planning the use of an equipment is to ensure:
A The equipment is not missing.
B Rotation and period of repairs
C Prove availability of the equipment.
D The registration of the equipment.
_____________________________________________
8. The principle of amortization of equipment
means:
A An amount taken from the output of the
equipment for its maintenance.
B Amount taken from its output for its
depreciation.
C Annual turnover of an equipment.
D The resulting price of an equipment.
_____________________________________________
9. Construction of structural elements
necessitating the use of lost formwork are:
A Pillars
B Floor slabs
C Complicated arches
D Dams
_____________________________________________
10. A commanding activity is an activity whose:
A Duration is important.
B Duration has influence on the contractual
duration of a project.
C Man power is important.
D Material consumption is high.
_____________________________________________
11. A critical path is:
A The path of major activities.
B The path whose activities are represented
with double lines.
C The shortest path to reach the end of the
project
D The path followed by commanding
activities.
_____________________________________________
12. The total margin is the:
A Difference in EFD and ESD
B Time for the activities to wa