  1. A Wall constructed to give lateral support to an existing wall is

    A Embankment wall

    B Retaining wall

    C Parapet wall

    D Buttress

  2. The term ‘ledger’ in scaffolding is defined as

    A The horizontal member of a scaffold

    B The vertical member of a scaffold

    C The diagonal member of a scaffold

    D The cross brace member of a scaffold

  3. Pile foundations are suitable for

    A Water logged soil

    B Multi-storey buildings

    C Compacted soils

    D Domestic building

  4. Basement wall is a wall that supports

    A Heavy loads

    B Vertical loads only

    C Vertical and horizontal loads

    D Horizontal loads only

  5. Which of the following shapes in figure 1 is a cylinder

    [Image showing 3 shapes]

    Figure 1

    A 1

    B 2

    C 3

    D 4

  6. Home comb Walls are also called

    A Curtain walls

    B Breast walls

    C Sleeper walls

    D Base walls

  7. The depth of an arch is the distance between

    A The crown and springing line

    B The crown and ground level

    C The intrados and extrados

    D Ground level and springing line

  8. Walls constructed above the roof are

    A Cavity walls

    B Sleeper walls

    C Parapet walls

    D Curtain walls

  9. The name given to the type of foundation in figure 2 is

    Figure 2

    A Raft foundation

    B Pad foundation

    C Stepped foundation

    D Pile foundation

  10. From figure 3, calculate the side A

    A 4.82 m

    B 4.80 m

    C 4.58 m

    D 4.00 m

  11. Given that 2R+G = 0.65m, Calculate G IF R

    A 31 m

    B 34 cm

    C 31 cm

    D 0.34 m

  12. Foundations are placed below ground level in order to increase

    A Stability of the structure

    B Strength of the structure

    C Workability of the structure

    D Durability of the structure

  13. Identify the part P as seen in figure 4

    Figure 4

    A Arm of the pillar

    B The width of the pillar

    C Gusset

    D Cantilever


PDF is loading please wait...

IL 2025 CONSTRUCTION PROCESS AND BUILDING PRACTICE 1


Leave a comment

Your email address will not be published. Required fields are marked *

JOIN OUR WHATSAPP GROUP! / REJOIGNEZ NOTRE GROUPE WHATSAPP!
sponsors Ads