WORK ORGANIZATION
a) Explain why in the installation of a site the following plumbing fixture ratios are not equal: 1 WC pour 20
workers, 1 lavatory for 10 workers and 1 shower for 8 workers.
(6 Marks)
b) The site in which you work in has a means of handling and transportation a crane. State the safety measures
you are to give a worker who is called upon to receive heavy loads in relationship to future handling of loads.

_________________________________________________________________________________________________

3. SITE PLANNING
The activities given in the table1, is the plan of the execution of a hydraulic project.

 

Activities Previous
Tasks
Duration
(Days)
Workers General
labors
A / 1 1 2
B / 1 1 2
C A 1 1 3
D B 2 3 2
E C 2 2 3
F C 3 2 3
G E 2 1 1
H FG 1 1 1
I D 3 1 2
J I 2 1 2
K HJ 1 1 2