cameroon gce advanced level plumbing project management 2
cameroon gce advanced level plumbing project management 2
WORK ORGANIZATION
a) Explain why in the installation of a site the following plumbing fixture ratios are not equal: 1 WC pour 20
workers, 1 lavatory for 10 workers and 1 shower for 8 workers. (6 Marks)
b) The site in which you work in has a means of handling and transportation a crane. State the safety measures
you are to give a worker who is called upon to receive heavy loads in relationship to future handling of loads.
_________________________________________________________________________________________________
3. | SITE PLANNING The activities given in the table1, is the plan of the execution of a hydraulic project. |
Activities | Previous Tasks |
Duration (Days) |
Workers | General labors |
A | / | 1 | 1 | 2 |
B | / | 1 | 1 | 2 |
C | A | 1 | 1 | 3 |
D | B | 2 | 3 | 2 |
E | C | 2 | 2 | 3 |
F | C | 3 | 2 | 3 |
G | E | 2 | 1 | 1 |
H | FG | 1 | 1 | 1 |
I | D | 3 | 1 | 2 |
J | I | 2 | 1 | 2 |
K | HJ | 1 | 1 | 2 |